The entire structural works, including the swimming pool decks, lobby, planters and internal parking areas are now 100% completed.
The brick walls of the apartments are also completed and we are progressing with 30% overall completion of plaster work and the first five units will be locked once completed mid February.
The landscape design is being revised and our landscape specialist is preparing trees, plants and bushes to be planted. We will begin the plantation of the large trees mid March to ensure a good growth.