- Progress on the residences is on schedule with all the block work (walls) of the apartments completed and we are now proceding with the wall plastering. Roof terrace beautification (walls) is in progress.
- The mockup unit is now furnished. We are now finalizing the furniture packages based on a careful selection of furniture, colors and textures.

-
The Resort Pool Villas are progressing on schedule with now 22 villas in construction at different stages. We are moving forward with all the foundations and structural elements of the villas, scheduled to be completed by the second week of February 2008.
-
Piling of the main facilities of the Resort is now 50% completed and we scheduled to finish all structural elements of the main facility by the end of March 2008.
|
|