Message from the Project Director - Mr. Thierry de Borde:
The Residences
- The apartments gypsum ceilings and flooring finishes are now completed.
- The elevators are now fully installed with the cabins and we are schedule to perform a complete operational test in mid-June.
- The residence is now connected to the permanent power.
- Please visit the Dewa Phuket www.dewaphuket.com website for the latest construction photos, located in the photo galleries section.
- Moving in the residence is set to start begining November 01. It is important for owners to make a decision for the furniture packages. A specific email on this has been sent to each owner. The furniture packages are also available for viewing and downloading on the website on the residence welcome page.

The Resort & Spa
- The block works of the pool villas will be completed by the end of June. We have now completed all the interior wall plastering of the pool villa.
- The main facility and main infrastructure are progressing on schedule. Please visit the website for photos of the main facility construction progress.
|
|